Build Your Dream Deck: A Weekend Warrior's Guide

9 min

Summer evenings on the grill, morning coffee over the backyard, a place for the family to spread out. An attached deck is one of the most rewarding projects a homeowner can take on, and with a solid plan you can build it yourself. This guide walks through every stage, from the permit to the last coat of stain.

Skill levelIntermediate
Time2–4 weekends
Steps22, in 7 stages
Before you digPermit + call 811
Let us price your deck for free

Send us your sketch and measurements. We'll do the material takeoff and quote every board, hanger and screw, so you buy it once.

Get a free takeoff →

Tools you'll need

  • Circular saw
  • Drill/driver and impact driver
  • 4 ft level and a line or laser level
  • Tape measure, chalk line, speed square, framing square
  • Post hole digger or auger
  • Stud finder
  • Safety glasses, hearing protection, gloves

Stage 1 Plan, permit and design

Step 1: Check local codes and get a permit

  • Call your city or county building department before you buy anything.
  • Ask about setbacks from property lines, height limits, guard (railing) rules and the required footing depth.
  • Ask which inspections they want during the build. Many want to see the footing holes before concrete goes in.

Step 2: Design your deck

  • Measure the wall where the deck will attach and decide the size, shape and height.
  • Think about sun, wind, privacy and where the door swings.
  • Draw a simple sketch with dimensions: ledger, beam, post locations and joist direction.
  • Joist size, beam size and post spacing all depend on your spans. Your permit plans and local span tables set them.

Tip: Bring your sketch to either store. We'll help check spans and build the full material list with you.

Step 3: Call 811 before you dig

  • Call 811 to have underground utilities marked. It's free.
  • Wait the required time (usually 2–3 business days) before digging.

Stage 2 Ledger, footings and posts

Step 4: Lay out the deck

  • Snap a chalk line on the house where the top of the ledger will sit.
  • Outline the deck with stakes and string.
  • Measure both diagonals. When they match, the layout is square.
  • Mark footing locations from your plan.

Step 5: Install the ledger board

  • Remove the siding where the ledger goes. A ledger should never be fastened over siding.
  • Flash the wall and the top of the ledger so water can't get behind it.
  • Fasten the treated ledger into the house rim joist with ledger-rated structural screws or bolts.
  • Fastener size and spacing come from your local code and depend on joist span. Follow the screw maker's chart.

Most important step: Most deck failures happen at the ledger. Don't use nails, and don't skip the flashing.

Shop this step: Structural screws · Flashing tape · Treated lumber

Step 6: Dig the footing holes

  • Dig below your local frost line. Your building department sets the depth, and in our part of the country it's deep.
  • Make holes wide enough for the footing size on your plan, and clear out loose soil.
  • Schedule the footing inspection now if your town requires one.

Step 7: Pour footings and set posts

  • Add a few inches of gravel to each hole for drainage.
  • Pour concrete and set an elevated (standoff) galvanized post base in each footing while it's wet. It holds the post just above the concrete so the end stays dry.
  • Finish the top of the concrete slightly above the ground and slope it so water runs off.
  • Let the concrete cure (see the bag; usually 24–48 hours) before loading it.
  • Stand posts in the bases, plumb them on two sides, and brace them.

Shop this step: Concrete mix · Post bases

Step 8: Cut posts to height

  • Mark every post level with the ledger using a line level or laser.
  • Measure down from that mark by the beam depth plus the joist depth (for a beam that the joists sit on). A double 2x10 beam is 9¼ in. deep, not 1½ in.
  • Cut square and clean.

Stage 3 Beam and joists

Step 9: Build and set the beam

  • Build the beam from two or three treated boards (size from your plan), fastened together and crowned up.
  • Set it on the posts and fasten it with post cap connectors.
  • Check that it's level end to end.

Shop this step: Post caps

Step 10: Hang the joists

  • Mark joist spacing on the ledger (usually 16 in. on center; some composite boards and diagonal layouts need 12 in.).
  • Install joist hangers on the ledger with the nails the hanger maker specifies. Ordinary deck screws aren't rated for hangers.
  • Set each joist in its hanger and across the beam. Keep the crowns up.
  • Secure joists to the beam with hurricane ties or the connector your plan calls for.

Shop this step: Joist hangers · Joist hanger nails

Step 11: Add the rim joist and blocking

  • Fasten a rim joist across the outer ends of the joists. It runs parallel to the ledger.
  • Add blocking between joists at mid-span to keep them straight.
  • Check the frame for square one more time before decking.

Stage 4 Deck boards

Step 12: Install the deck boards

  • Start with a straight board along the house, leaving a small gap at the wall for drainage.
  • Fasten with two screws at every joist. Pre-drill near board ends to prevent splitting.
  • Gap boards evenly (typically â…›–¼ in. for wood; follow the maker's spacing for composite).
  • Stagger butt joints, and land every joint on a joist.

Shop this step: Decking · Deck screws

Step 13: Trim the edge

  • Let boards run long, then snap a chalk line and cut them all at once with a circular saw.
  • Ease rough edges with sandpaper.

Stage 5 Railing

Most codes require a guard when the deck surface is more than 30 in. above the ground, and the guard must be at least 36 in. tall at a home. Openings must stop a 4 in. ball. Check your local rules.

Step 14: Install railing posts

  • Space posts per your railing system or plan.
  • Bolt posts to the rim joist with added blocking or post-to-joist hardware. Avoid notching posts; it weakens them.
  • Make sure every post is plumb and the same height.

Step 15: Install rails and balusters

  • Cut top and bottom rails to fit between posts. Set the bottom rail a few inches above the deck.
  • Cut balusters and space them so no gap is 4 in. or more.
  • Optional: add a 2x6 cap rail across the top for a finished look and a place to set a drink.

Shop this step: Railing kits

Stage 6 Stairs

Step 16: Figure the stair layout

  • Measure the total rise from the landing spot to the top of the deck.
  • Divide it into equal steps. Under the IRC, used by most towns, each riser can be no more than 7¾ in. and each tread at least 10 in. deep.
  • Plan a solid landing at the bottom: a concrete pad or compacted gravel.

Step 17: Cut and set the stringers

  • Lay out one stringer on a treated 2x12 with a framing square, cut it, and test the fit.
  • Use it as the pattern for the rest, or start from precut treated stringers.
  • Attach stringers to the deck frame with hangers or brackets and rest them on the landing.

Shop this step: Stair stringers

Step 18: Install treads

  • Fasten treads to every stringer and check each one for level.
  • Add risers if you want a closed look.
  • Add a graspable handrail if your stairs have four or more risers (check local code).

Stage 7 Finish and inspection

Step 19: Sand and clean

  • Sand splinters, especially on rails and stair treads.
  • Sweep off sawdust and debris.

Step 20: Stain or seal

  • New treated lumber often needs to dry out before it takes stain. Sprinkle water on it: if it beads, wait.
  • Apply in the shade, following the can's directions and dry times.

Shop this step: Deck stain

Step 21: Final inspection

  • Schedule your final inspection.
  • Recheck every connection, railing and stair for tightness.

Step 22: Keep it in shape

  • Inspect connections, boards and railings every spring.
  • Clean the surface and reapply stain or sealer every 2–3 years.
  • Replace soft or cracked boards right away.

Safety reminders

  • Wear safety glasses and hearing protection.
  • Get a helper for beams, joists and anything overhead.
  • Use hot-dip galvanized or stainless fasteners rated for treated lumber.
  • Measure twice, cut once, and don't rush.
Questions on your deck?

Call Akron at 712-568-2801 or Crofton at 402-388-4330, or send us your plans for a free takeoff.

Get a free takeoff →

Building codes vary by town. This guide covers general practice. Your local building department's rules and your approved plans come first.

10 items found
Sort by
Transcend Lineage Composite Deck Boards – Cool, Durable, & Stylish
12' Fascia Boards, Composite Decking (Pick Your Width)
5/4 in. x 6 in. x 10 ft. Standard Green Deck Board
5/4 in. x 6 in. x 12 ft. Standard Green Deck Board
5/4 in. x 6 in. x 14 ft. Standard Green Deck Board
5/4 in. x 6 in. x 16 ft. Standard Green Deck Board
Total 10 products
10 items found
Sort by
Transcend Lineage Composite Deck Boards – Cool, Durable, & Stylish
12' Fascia Boards, Composite Decking (Pick Your Width)
5/4 in. x 6 in. x 10 ft. Standard Green Deck Board
5/4 in. x 6 in. x 12 ft. Standard Green Deck Board
5/4 in. x 6 in. x 14 ft. Standard Green Deck Board
5/4 in. x 6 in. x 16 ft. Standard Green Deck Board
Total 10 products

Build Your Dream Deck: A Weekend Warrior's Guide

9 min

Summer evenings on the grill, morning coffee over the backyard, a place for the family to spread out. An attached deck is one of the most rewarding projects a homeowner can take on, and with a solid plan you can build it yourself. This guide walks through every stage, from the permit to the last coat of stain.

Skill levelIntermediate
Time2–4 weekends
Steps22, in 7 stages
Before you digPermit + call 811
Let us price your deck for free

Send us your sketch and measurements. We'll do the material takeoff and quote every board, hanger and screw, so you buy it once.

Get a free takeoff →

Tools you'll need

  • Circular saw
  • Drill/driver and impact driver
  • 4 ft level and a line or laser level
  • Tape measure, chalk line, speed square, framing square
  • Post hole digger or auger
  • Stud finder
  • Safety glasses, hearing protection, gloves

Stage 1 Plan, permit and design

Step 1: Check local codes and get a permit

  • Call your city or county building department before you buy anything.
  • Ask about setbacks from property lines, height limits, guard (railing) rules and the required footing depth.
  • Ask which inspections they want during the build. Many want to see the footing holes before concrete goes in.

Step 2: Design your deck

  • Measure the wall where the deck will attach and decide the size, shape and height.
  • Think about sun, wind, privacy and where the door swings.
  • Draw a simple sketch with dimensions: ledger, beam, post locations and joist direction.
  • Joist size, beam size and post spacing all depend on your spans. Your permit plans and local span tables set them.

Tip: Bring your sketch to either store. We'll help check spans and build the full material list with you.

Step 3: Call 811 before you dig

  • Call 811 to have underground utilities marked. It's free.
  • Wait the required time (usually 2–3 business days) before digging.

Stage 2 Ledger, footings and posts

Step 4: Lay out the deck

  • Snap a chalk line on the house where the top of the ledger will sit.
  • Outline the deck with stakes and string.
  • Measure both diagonals. When they match, the layout is square.
  • Mark footing locations from your plan.

Step 5: Install the ledger board

  • Remove the siding where the ledger goes. A ledger should never be fastened over siding.
  • Flash the wall and the top of the ledger so water can't get behind it.
  • Fasten the treated ledger into the house rim joist with ledger-rated structural screws or bolts.
  • Fastener size and spacing come from your local code and depend on joist span. Follow the screw maker's chart.

Most important step: Most deck failures happen at the ledger. Don't use nails, and don't skip the flashing.

Shop this step: Structural screws · Flashing tape · Treated lumber

Step 6: Dig the footing holes

  • Dig below your local frost line. Your building department sets the depth, and in our part of the country it's deep.
  • Make holes wide enough for the footing size on your plan, and clear out loose soil.
  • Schedule the footing inspection now if your town requires one.

Step 7: Pour footings and set posts

  • Add a few inches of gravel to each hole for drainage.
  • Pour concrete and set an elevated (standoff) galvanized post base in each footing while it's wet. It holds the post just above the concrete so the end stays dry.
  • Finish the top of the concrete slightly above the ground and slope it so water runs off.
  • Let the concrete cure (see the bag; usually 24–48 hours) before loading it.
  • Stand posts in the bases, plumb them on two sides, and brace them.

Shop this step: Concrete mix · Post bases

Step 8: Cut posts to height

  • Mark every post level with the ledger using a line level or laser.
  • Measure down from that mark by the beam depth plus the joist depth (for a beam that the joists sit on). A double 2x10 beam is 9¼ in. deep, not 1½ in.
  • Cut square and clean.

Stage 3 Beam and joists

Step 9: Build and set the beam

  • Build the beam from two or three treated boards (size from your plan), fastened together and crowned up.
  • Set it on the posts and fasten it with post cap connectors.
  • Check that it's level end to end.

Shop this step: Post caps

Step 10: Hang the joists

  • Mark joist spacing on the ledger (usually 16 in. on center; some composite boards and diagonal layouts need 12 in.).
  • Install joist hangers on the ledger with the nails the hanger maker specifies. Ordinary deck screws aren't rated for hangers.
  • Set each joist in its hanger and across the beam. Keep the crowns up.
  • Secure joists to the beam with hurricane ties or the connector your plan calls for.

Shop this step: Joist hangers · Joist hanger nails

Step 11: Add the rim joist and blocking

  • Fasten a rim joist across the outer ends of the joists. It runs parallel to the ledger.
  • Add blocking between joists at mid-span to keep them straight.
  • Check the frame for square one more time before decking.

Stage 4 Deck boards

Step 12: Install the deck boards

  • Start with a straight board along the house, leaving a small gap at the wall for drainage.
  • Fasten with two screws at every joist. Pre-drill near board ends to prevent splitting.
  • Gap boards evenly (typically â…›–¼ in. for wood; follow the maker's spacing for composite).
  • Stagger butt joints, and land every joint on a joist.

Shop this step: Decking · Deck screws

Step 13: Trim the edge

  • Let boards run long, then snap a chalk line and cut them all at once with a circular saw.
  • Ease rough edges with sandpaper.

Stage 5 Railing

Most codes require a guard when the deck surface is more than 30 in. above the ground, and the guard must be at least 36 in. tall at a home. Openings must stop a 4 in. ball. Check your local rules.

Step 14: Install railing posts

  • Space posts per your railing system or plan.
  • Bolt posts to the rim joist with added blocking or post-to-joist hardware. Avoid notching posts; it weakens them.
  • Make sure every post is plumb and the same height.

Step 15: Install rails and balusters

  • Cut top and bottom rails to fit between posts. Set the bottom rail a few inches above the deck.
  • Cut balusters and space them so no gap is 4 in. or more.
  • Optional: add a 2x6 cap rail across the top for a finished look and a place to set a drink.

Shop this step: Railing kits

Stage 6 Stairs

Step 16: Figure the stair layout

  • Measure the total rise from the landing spot to the top of the deck.
  • Divide it into equal steps. Under the IRC, used by most towns, each riser can be no more than 7¾ in. and each tread at least 10 in. deep.
  • Plan a solid landing at the bottom: a concrete pad or compacted gravel.

Step 17: Cut and set the stringers

  • Lay out one stringer on a treated 2x12 with a framing square, cut it, and test the fit.
  • Use it as the pattern for the rest, or start from precut treated stringers.
  • Attach stringers to the deck frame with hangers or brackets and rest them on the landing.

Shop this step: Stair stringers

Step 18: Install treads

  • Fasten treads to every stringer and check each one for level.
  • Add risers if you want a closed look.
  • Add a graspable handrail if your stairs have four or more risers (check local code).

Stage 7 Finish and inspection

Step 19: Sand and clean

  • Sand splinters, especially on rails and stair treads.
  • Sweep off sawdust and debris.

Step 20: Stain or seal

  • New treated lumber often needs to dry out before it takes stain. Sprinkle water on it: if it beads, wait.
  • Apply in the shade, following the can's directions and dry times.

Shop this step: Deck stain

Step 21: Final inspection

  • Schedule your final inspection.
  • Recheck every connection, railing and stair for tightness.

Step 22: Keep it in shape

  • Inspect connections, boards and railings every spring.
  • Clean the surface and reapply stain or sealer every 2–3 years.
  • Replace soft or cracked boards right away.

Safety reminders

  • Wear safety glasses and hearing protection.
  • Get a helper for beams, joists and anything overhead.
  • Use hot-dip galvanized or stainless fasteners rated for treated lumber.
  • Measure twice, cut once, and don't rush.
Questions on your deck?

Call Akron at 712-568-2801 or Crofton at 402-388-4330, or send us your plans for a free takeoff.

Get a free takeoff →

Building codes vary by town. This guide covers general practice. Your local building department's rules and your approved plans come first.